Redirection in 10 seconds

.

12/13/2007

News 2008 - 2009

During the winter closing of the park big works are finally going to be able to begin:
- At the Beginning of January, 08 the beginning of works of the displacement of the road which will have to be finished before March 15th (date of reopening of the park).
- At the Beginning of April, 08 start of works of the extension of the park of 15ha and at the beginning of the building of the new coaster (certain pillars are besides already marked on the soil).
- In April, 09, in the reopening of the park, the coaster will be finished but also the second left the Portuguese quarter.

From other information to come on the coaster shortly !

And therefore for 2008, they begin knowing about it a little more every days:
- There will be the 2 flat-rides in the quarter English first of all.
- Undoubtedly a rehabilitation of Eurosat :

- The film of Magic Cinéma 4D should change: title should be "Atlantis".

- A rehabilitation of the pirates of Batavia will take place, as well as the development of a restaurant (plan left in 1991) inside this last instead of the jungle :



Aucun commentaire: